Serbian Power Grid Operator Ready to Connect 2.8 GW of Wind Farms

07 Aug 2021  by balkangreenenergynews.com   

State power grid operator Elektromre?a Srbije (EMS) has invested EUR 30 million in two overhead power lines in the Banat region of Vojvodina. which will enable the integration of 2.8 GW of wind farms that are in different phases of the connection process. This demonstrates that EMS is ready to meet the demand for the connection of new green power plants. However, she also said it will be a challenge to secure some EUR 60 million a year needed to ensure the transmission system can keep pace with the increasing demand for renewables integration.

Jelena Mateji? also talked about new requests for the connection of solar and wind power plants, the power grid operator’s experience with the variable output of wind farms that are already connected, as well as the completion of the Trans-Balkan Electricity Corridor.

Investors are announcing the construction of green energy power plants with a capacity of between several hundred megawatts and several gigawatts.

How prepared is EMS to integrate new wind farms, solar parks, hydropower plants?

As the national transmission system operator, EMS is channeling its infrastructure investments taking into account several key objectives, including the integration of renewable energy sources. In line with this, and in an effort to meet the objectives of the Energy Sector Development Strategy of the Republic of Serbia until 2025 with projections until 2030, EMS has completed two capital infrastructure projects in southern Banat: a double-circuit 400 kV overhead power line between the Pan?evo 2 substation and the Romanian border (Section1 of the Trans-Balkan Electricity Corridor) and a 110 kV overhead line between the Bela Crkva substation and the Veliko Gradište substation.

EMS invested nearly EUR 30 million of its own funds in these two projects alone. I’m telling you this because these projects are significant precisely because their implementation has enabled the integration of a certain number of wind farms in this region, where there are currently a total of 2.8 GW of wind power plants in different phases of the connection process. So, we’re ready. We are working and we are looking at all the needs of investors, as well as the capacities of our system and, after all, of Serbia as a country.

How much does EMS need to invest in the connection of new capacities?

Over the coming period, EMS will need to make massive investments to enable a greater level of renewable energy integration. The necessary annual investments that would enable the adequate development of EMS’ transmission system, with the necessary maintenance of the existing grid, are analyzed in a study on a long-term development of Serbia’s power transmission system until 2035, produced by Electrical Engineering Institute Nikola Tesla, as a consultant.

We expect significant support from the state budget for future investments given that these are capital and strategic projects that will help achieve national goals

Based on the results of the study, and available data from practical experience, it has been determined that it is necessary to invest nearly EUR 60 million a year in order to ensure that the development of the power transmission system can keep pace with the increasing demand for renewable energy integration. Otherwise some projects could be delayed, limiting EMS’ capacity to respond adequately to the energy transition.

How are you going to secure the necessary funding?

These are clearly significant investments that require sizeable funds. EMS has experience in implementing major infrastructure projects, and over the years it has relied on its own funds as well as loans and credit arrangements with international financial institutions. It will be the same with these investments, but this time around we certainly expect significant support from the state budget given that these are capital and strategic projects that will help achieve our national goals.

What other parts of the transmission system is EMS currently investing in?

We aim to ensure the greatest possible stability and security of supply for electricity consumers, as well as an unimpeded integration of the greatest possible capacity of renewable energy sources.

Projects that should be mentioned are the construction of a 400 kV overhead line between the Kragujevac 2 substation and the Kraljevo 3 substation (Section2 of the Trans-Balkan Corridor), as well as a double-circuit 400 kV overhead line between the Obrenovac substation and the Bajina Bašta substation (Section 3 of the Trans-Balkan Corridor). The completion of these projects will enable an unimpeded offtake of electricity from hydropower capacities in the Drina-Lim river basin, where the current installed capacity exceeds 1.1 GW.

EMS is also working on the rollout of new technologies

Additionally, a significant portion of EMS’ investments is channeled towards the further development of the transmission system in southern Banat and an increase of the transmission capacity between this area and the rest of the country, including, first and foremost, the BeoGrid2025 project, which entails the construction of a new 400/110 kV substation called Beograd 50 and a new double-circuit 400 kV overhead line that will connect this facility with southern Banat. This will open up another corridor for supplying electricity produced from renewable energy sources to consumers in the Srem region.

In parallel with infrastructure development, EMS is working on the rollout of new technologies. We have completed a pilot project of installing a Dynamic Line Rating (DLR) device with the aim of making the existing infrastructure more flexible amid intensified renewable energy integration. This technology can be considered an operational solution to problems arising from increased electricity generation at wind power plants due to high wind speeds.

What is EMS’ experience with the 400 MW of wind capacities that are already connected to the grid?

At the moment, there are four wind farms connected to the transmission system – ?ibuk 1, at 400 kV, Kova?ica, at 220 kV, and Alibunar and Košava, at 110 kV – whose total installed capacity is 374 MW. The share of these four wind farms in overall electricity production in Serbia in 2020 was 2.6%. The experience so far has been positive and there have been no problems on the grid due to the operation of these wind farms.

How problematic for the transmission system is the intermittency of this energy source?

Given the current share of these wind farms in overall electricity production, and the combined installed capacity of all power plants connected to the grind, the intermittency of these sources does not affect the stability of the transmission system.

EMS has a good relationship with all four wind farms, which is defined in agreements on the operation of these facilities. These agreements set out the responsibilities and obligations regarding the operation of these specific sources of electricity.

In line with the best practices of European grids where renewable energy sources have a significant impact on the functioning of the system, EMS has established a forecasting process for electricity generation from renewable energy sources in order to minimize the impact of their intermittency. For now these forecasts, which are made on a daily and weekly basis, are within the set limits (the average error is about 10% of the installed capacity), which provides satisfactory parameters for management in real time.

What is the total installed capacity of new facilities whose connection is pending?

At the moment, the requested capacity for connection is 4,274 MW for wind farms, 637 MW for solar power plants, and 750 MW for thermal power plants.

What is your assessment of the feasibility of these projects?

The offtake of electricity produced at power plants using renewable energy sources, from the standpoint of the transmission system operator’s jurisdiction, will be enabled in line with the newly adopted regulatory framework, and at a pace at which investors can realize their wind and solar projects and the defined connection procedure.

At what stage is the construction of the Trans-Balkan Corridor?

It is well known that this project is a strategic investment of regional and European significance. The Trans-Balkan Corridor is primarily aimed at ensuring Serbia’s national energy security and replacing the outdated lower-voltage network (220 kV) with a higher-voltage system whose capacity is many times bigger. The project will also improve the security of supply in western and central Serbia. Thanks to its geographical position and planned investments in new interconnections, the Trans-Balkan Corridor is at the same time a kind of a link between the East and the West, connecting the markets of eastern and western Europe.

The project consists of four sections. Section 1, which involved building a double-circuit 400 kV overhead line between Pan?evo and the Romanian border and equipping  the 400 kV field at the 400/220/110 kV Pan?evo 2 substation, was completed and put in operation in December 2017, and was financed entirely with EMS’ own funds.

When it comes to Section 2 – the construction of a 400 kV overhead line between Kragujevac 2 and Kraljevo 3 (60 kilometers in length), the upgrade of the 220/110 kV Kraljevo 3 substation into a 400/220/110 kV substation, and the fitting of the 400 kV field at the 400/110 kV Kragujevac 2 substation – the works were launched in 2020. The transmission line is expected to be completed this year, while works on Kraljevo 3 should be finished in 2022, marking the completion of the entire Section 2.

Section 3 (building a double-circuit 400 kV overhead power line between the Obrenovac and Bajina Bašta substations, increasing the voltage level at Bajina Bašta to 400 kV, and equipping the 400 kV field at the 400/220 kV Obrenovac substation) should be completed by the end of 2025, while Section 4 (a double-circuit 400 kV overhead line from the Bajina Bašta substation to the borders with Montenegro and Bosnia and Herzegovina) is planned to be put in operation in 2026.

More News

Loading……
国产黄色在线观看| 国产男小鲜肉同志免费| 欧美日韩黄视频| 91国产免费观看| 91精品中文字幕一区二区三区| 777午夜精品视频在线播放| 日韩免费成人网| 快色在线观看| 成年午夜在线| 男人天堂视频在线观看| 日韩不卡视频在线观看| 亚洲欧美日本国产| 亚洲国产最新| 国产综合欧美| 日韩成人dvd| 成人夜色视频网站在线观看| 国产精品国产三级国产普通话蜜臀| 亚洲综合区在线| 欧美日韩高清影院| 原千岁中文字幕| 精产国品自在线www| www.久久| 97精品一区二区| 欧美96一区二区免费视频| 2021久久国产精品不只是精品| 中文字幕中文字幕中文字幕亚洲无线| 亚洲国产一区二区三区| 91精品国产综合久久久久| 永久www成人看片| 国产黄色大片在线观看| 国产精品久av福利在线观看| 欧美a级一区| 岛国精品在线观看| 一区二区国产视频| 人人澡人人爽人人揉| 日本综合在线| 人人爱人人干婷婷丁香亚洲| 欧美一区成人| 97久久超碰精品国产| 色诱视频网站一区| 尤物视频网站在线观看| 国产免费不卡| 国产精品久久久久无码av| 国产米奇在线777精品观看| 亚洲欧洲精品天堂一级 | 宅男在线一区| 美女视频一区在线观看| 亚洲欧洲日韩av| 日韩网站在线看片你懂的| av中文字幕在线| 亚洲精品高潮| 日本大胆欧美人术艺术动态| 亚洲色图欧美激情| 日本桃色视频| 亚洲成a人片| 精品99视频| 亚洲情趣在线观看| 精品美女调教视频| 巨茎人妖videos另类| 欧美区国产区| 中文字幕一区二区三区视频| 蜜桃特黄a∨片免费观看| 老牛影视精品| 激情欧美日韩一区| 成人免费视频在线观看| 亚洲精品666| 青草综合视频| 六月丁香综合在线视频| 色吊一区二区三区| 黄色网在线播放| 日韩在线中文| 中文字幕一区二区在线观看| 国产视频青青| 国产精品美女久久久久人| 蜜臀久久99精品久久久画质超高清 | 在线观看a视频| 不卡视频在线| 国产精品国产三级国产有无不卡| 特黄aaaaaaaaa毛片免费视频| 成人全视频在线观看在线播放高清| 欧美亚洲不卡| 福利微拍一区二区| 日本片在线观看| 国产欧美三级| 欧美午夜在线一二页| 国模精品视频| 日本人妖一区二区| 欧美一级片在线看| 四虎视频在线精品免费网址| 久久99精品久久久| 精品处破学生在线二十三| 精品肉辣文txt下载| 狠狠色丁香久久婷婷综| 欧美v国产在线一区二区三区| 成人黄页网站视频| 卡一卡二国产精品| 日韩欧美国产精品一区| 欧美不卡在线观看| 95精品视频在线| 2023欧美最顶级a∨艳星| 伊人久久大香线蕉无限次| 国产人成亚洲第一网站在线播放 | 日韩免费看网站| 免费精品一区二区三区在线观看| 成人精品鲁一区一区二区| 探花国产精品| 日韩久久电影| 欧美性大战久久| 成人精品高清在线视频| 国产成人综合视频| 中文字幕免费在线视频| 在线一区免费| 91精品国产丝袜白色高跟鞋| 日韩欧美一级| 一区二区三区自拍| 黑人巨大亚洲一区二区久 | 欧美日韩午夜影院| 国产精品1区在线| 国产精品女人毛片| 国产理论电影在线| www.66久久| 久久77777| 国产在线一区观看| 亚洲啪啪aⅴ一区二区三区9色| 欧美日韩mv| 中文字幕高清20页| 婷婷亚洲最大| 精品国产一区二区精华| 波多野结衣在线播放一区| 欧美日免费三级在线| 婷婷国产精品| 欧美日韩日日摸| 欧美日韩播放| 日韩一二三区视频| 青青草国产成人a∨下载安卓| 欧美日韩一级二级| 成人网18免费网站| 欧美一级xxx| 亚洲色图二区| 国产色视频网站| 在线亚洲成人| 青青操在线视频| 国产毛片一区二区| 麻豆av在线导航| 91视频www| 老司机成人影院| 亚洲综合在线第一页| 色悠久久久久综合先锋影音下载| 亚洲午夜免费视频| 狼人精品一区二区三区在线| 欧美亚洲一区二区在线| 欧美日韩在线播放视频| 天天操天天艹| 亚洲美女啪啪| 香蕉网站在线| 成人av在线资源| 欧美影视资讯| 疯狂做受xxxx欧美肥白少妇| 亚洲专区视频| 欧美成人bangbros| 久久一区国产| 成人在线影视| 亚洲色图欧美在线| 日韩精品导航| www.4438全国最大| 国产在线精品一区二区三区不卡| av网站大全在线| 亚洲色图一区二区三区| 日韩av中文字幕一区| 天天色天天上天天操| 日本成人在线不卡视频| 里番在线播放| 粉嫩av一区二区三区免费野| 国产精品成人av| 日本福利片高清在线观看| 成人激情动漫在线观看| 日韩免费在线电影| 日韩一区二区三区免费观看| 天堂一区二区在线| 五月天av在线| 欧美少妇bbb| 日本不卡的三区四区五区| 51av在线| 欧洲精品一区二区| 久久黄色影院| 欧美xoxoxo| 日韩三区在线观看| 精品午夜一区二区三区在线观看| 天堂在线中文网官网| 欧美日韩久久久久| 亚洲久久视频| 男人久久天堂| 91麻豆精品国产91久久久资源速度 | 免费观看在线综合色| 性欧美18xxxhd| 91精品久久久久久久91蜜桃| 日韩国产精品久久久| 久久麻豆视频| 九色中文视频| 国产精品成人午夜|