Canadian Provinces Reach Multi-Billion Dollar Deal Over Power From Churchill Falls Hydroelectric Plant

13 Dec 2024   

They’re tearing up treaties in the Great White North. Literally.

At a packed press conference today in its capital of St. John’s, Newfoundland and Labrador Premier Andrew Furey ripped up a piece of paper signifying the end of a 65-year-old contract with fellow Canadian province Québec that many argue unfairly compensated N.L. for power generated from the Churchill Falls hydroelectric plant.

“?Today, everything changes for Newfoundland and Labrador,” Furey said, summoning a round of applause that lasted a full 15 seconds. “After more than 50 years of a lopsided agreement that has been such a contentious point for Newfoundland and Labrador, we finally have a new deal on the table for Churchill Falls with Québec.”

“We are ripping up the 1969 contract,” Furey exclaimed to the excitement of the room. “Not in 2041, when it expires, but today.”

In its place, Furey and Québec Premier François Legault signed a long-discussed memorandum of understanding, expected to be finalized in 2026, that would mean a staggering $200 billion for each province over the next five decades. It includes plans to develop Gull Island, recognized as one of the few remaining prime locales for hydroelectric development in North America.

What’s in it for them?

For Newfoundland and Labrador, it means at least 30 times more money from power generated at the 5,428-megawatt (MW) Churchill Falls underground power station in Labrador, the second-largest hydro facility in Canada.

Under the old deal, N.L. received just 0.2 cents per kilowatt-hour (kWh). The new proposal kicks back at least 5.9 cents/kWh.

According to CBC, N.L. will earn $1 billion per year for the next 17 years. Starting in 2041, that will double to $2 billion, then double again to $4 billion in 2056, and could increase even further pending escalation clauses in the agreement.

Premier Legault called it a “win-win” deal, noting its benefits for Québec in turn, which include securing reliable, clean, and affordable electricity in an era of soaring demand.

The agreement will guarantee access to 7,200 MW for the next 50 years at a lower price than any other renewable option in North America, according to government-owned electric utility Hydro-Québec. The agreement not only renews Québec’s access to existing Churchill Falls generation but also adds new production through increased capacity at the existing facility, the development of a new generation station on the Churchill Falls site, as well as the new proposed facility at Gull Island.

In total, the utility expects to generate 9,190 MW, 7,200 MW of which will be purchased by Hydro-Québec and 1,990 by Newfoundland and Labrador Hydro. That includes a proposed increase of hydroelectric production at Churchill Falls via a second powerhouse built near the existing reservoir that would generate 1,110 MW.

“In an increasingly uncertain world, it’s an advantage for Québec to have greater certainty over its energy security,” said Canada’s deputy minister of finance Michael Sabia. “For the next 50 years, we are assured of a realistic financial structure that guarantees the affordability of electricity and the profitability of Hydro-Québec.”

The average net cost for power from the existing Churchill Falls site will be 4 cents/kWh, in 2024 dollars. The average price for electricity from the new developments will be 11 cents/kWh, which is below the generation price forecast in Hydro-Québec’s decarbonization playbook Action Plan 2035, which is 13 cents/kWh. Together, Hydro-Québec points out, the average cost of all electricity from Labrador will be 6 cents/kWh- half the price of the renewable alternatives available to Québec.

“This agreement is an important step towards decarbonizing Québec and protecting our environment. It is an essential contribution to our collective wealth,” Sabia added. “This agreement is a win for citizens, a win for the economy, and of course, a win for future generations.”

Developing Gull Island

The second part of the memorandum of understanding between N.L. and Québec revolves around an undeveloped project downstream of the Churchill River.

In 2011, the Canadian government said it would back a loan to fund the first phase of the 3,074-MW Lower Churchill project proposed by crown energy company Nalcor Energy. The project called for an 824 MW hydroelectric plant at Muskrat Falls, a 2,250 MW facility at Gull Island, and 130 miles of subsea transmission that would carry the power around Québec’s border to Nova Scotia, where it could then be sold to the United States.

Under the new agreement, the remaining part of the project, Gull Island, would be a tag-team joint venture between N.L. Hydro (60%) and Hydro-Québec (40%). Hydro-Québec would lead and manage its construction and absorb any associated extra costs. N.L. Hydro would operate the facility and have access to 225 MW of its generation.

“If you consult any expert in North America, they will all tell you that it’s the best project in North America,” Legault told the room to its immediate cheerful approval. “I wanted to be a part of it.”

N.L. Hydro would also get access to 135 MW of the aforementioned proposed Churchill Falls expansion. The provinces are considering also upgrading existing Churchill Falls units, which would increase production to 550 MW.

In totality, today’s tentative agreement is momentous for both provinces.

“It’s a very important contract for Québec,” Legault added, noting it represents 15% of the total capacity of Hydro-Québec. “It’s really key for us.”

“Together with Québec, we are starting a new chapter,” echoed N.L. Premier Furey. “While we can’t change the past, we can use it as the opening lines of a bold new chapter of our province, and in this moment, change our future.”

More News

Loading……
日韩mv欧美mv国产网站| а√天堂中文在线资源8| 你懂的视频在线免费| 免费在线一级视频| 毛片在线视频| 在线观看v片| 亚洲网站免费| 日韩欧美天堂| 国内精品福利| 一区久久精品| 人人超碰91尤物精品国产| 免费一级欧美片在线观看| 国产精品自产自拍| 欧美国产在线观看| 欧美日韩国产页| 精品国精品国产| 蜜臀一区二区三区| 国产在线观看免费麻豆| 88xx成人免费观看视频库| 亚洲精品国产九九九| 天天久久综合| 日韩黄色在线观看| 久久综合色鬼综合色| 亚洲aⅴ怡春院| 四虎永久在线高清国产精品| 韩国三级在线观看久| 高清电影在线观看免费| 美女久久精品| 一区二区亚洲| 99国产精品久久久久久久久久久| 亚洲精品国产高清久久伦理二区| 欧美日本国产一区| 青草久久伊人| 欧洲午夜精品| 亚洲性视频h| 91老师国产黑色丝袜在线| 欧美视频专区一二在线观看| 明星乱亚洲合成图.com| 黄色在线播放网站| 97青娱国产盛宴精品视频| 亚洲二区免费| 中文字幕一区二区三中文字幕| 欧美久久一区二区| 91大神在线网站| 欧美最新精品| 欧美精品导航| 欧美国产精品中文字幕| 日韩欧美综合一区| 日本动漫理论片在线观看网站 | 天天综合天天| 丁香花在线观看完整版电影| 欧美**字幕| 成人精品在线视频观看| 日本高清无吗v一区| 青青草av免费在线观看| 国模大尺度视频一区二区| 一本久久知道综合久久| 中文字幕一区三区| 美女无遮挡网站| 四虎成人在线| 麻豆精品网站| 欧美天天综合色影久久精品| 免费在线一级视频| 免费欧美激情| 成人黄色小视频在线观看| 欧美精品1区2区3区| 欧美大片黄色| 黄色成人av网站| 亚洲欧美韩国综合色| 欧美性猛交p30| 综合欧美亚洲| 不卡视频在线看| 日韩视频一区二区在线观看| 91超碰在线| 午夜在线视频观看日韩17c| 亚洲人成小说网站色在线| 在线免费观看av网站| 久久99精品久久久久久欧洲站| 国产乱国产乱300精品| 日韩午夜精品视频| 精品九九久久| 国产一区在线看| 欧美va亚洲va| 国产精一区二区| 国产成人激情av| 国产乱妇乱子| 亚洲v天堂v手机在线| 99国产精品视频免费观看| 男人的天堂网av| 日韩电影不卡一区| 国产精品欧美一区喷水| 欧美视频综合| 欧美黄色一区| 色先锋aa成人| 久久精品女人天堂av免费观看| 丝袜亚洲另类欧美| 日韩西西人体444www| 9999在线精品视频| 99re视频这里只有精品| 香蕉视频在线观看免费| 欧美中文字幕一区二区| 亚洲va国产va欧美va观看| 538在线视频| 久久成人久久鬼色| 激情婷婷丁香| 国产精品国内免费一区二区三区| 亚洲成人777| 成人欧美大片| 99re在线精品| 嫩草在线视频| 奇米色一区二区三区四区| 天天插天天色| 日韩精品一区二区三区免费观影| 性做久久久久久久免费看| 少妇视频一区| 2023国产精品视频| 国产黄a三级三级三级av在线看| 亚洲精品乱码久久久久久蜜桃麻豆| 欧美日韩高清不卡| 高清精品视频| 午夜精品视频在线观看| 成人精品电影在线| 成人午夜在线视频| 最新97超碰在线| 激情综合色播激情啊| 涩爱av在线播放一区二区| 亚洲日本视频| 999大胆视频| 欧美视频一区| h片免费观看| 欧美午夜免费影院| 高清毛片aaaaaaaa**| 欧美激情91| 2020中文字幕在线| 欧美另类亚洲| av五月婷婷| 国产精品亚洲综合色区韩国| 开心快乐六月丁香婷婷| 亚洲国产黄色| 中文在线一二区| 日本午夜一本久久久综合| 在线天堂视频| 久久成人麻豆午夜电影| 成人免费高清在线播放| 激情文学综合插| 日本在线天堂| 91免费看`日韩一区二区| а√天堂8资源在线| 成人免费一区二区三区在线观看| 欧美日韩女优| 精品福利在线观看| 国产精品午夜一区二区三区| 日韩亚洲欧美中文三级| 中文字幕一区二区av| 日本成在线观看| 日韩和欧美的一区| 成人直播在线| 中文字幕一区二| 136国产福利精品导航网址应用| 日韩欧美高清视频| 欧美韩国日本在线观看| 日本特黄a级高清免费大片| 日本aⅴ免费视频一区二区三区 | 粉嫩老牛aⅴ一区二区三区 | 国产系列在线观看| 91网站最新网址| 婷婷激情成人| 欧美日韩一区小说| 亚洲免费成人| 黄色网址在线免费| 最近中文字幕一区二区三区| 99re热精品视频| 天天操天天擦| 久久精品噜噜噜成人av农村| 黄网在线免费看| 一区二区三区四区视频精品免费 | 喷水一区二区三区| 黄色一级视频网站| 丰满亚洲少妇av| 国产精品二区不卡| 青青草娱乐在线| 欧美人与禽zozo性伦| 久久久五月婷婷| 五月精品视频| 中文字幕精品影院| 青青久在线视频| 一本久久a久久精品亚洲| 久久99久久99小草精品免视看| 综合久久成人| 国产网站在线| 欧美日韩aaaaaa| 亚洲国产精品精华液ab| 久久久久国产一区二区| 在线成人超碰| 日韩av不卡一区| 96久久久久久| 精品国产乱码久久久久久影片| 香蕉成人伊视频在线观看| 一区二区三区免费在线观看| 国产一区在线观看麻豆|