日韩福利电影在线_久久精品视频一区二区_亚洲视频资源_欧美日韩在线中文字幕_337p亚洲精品色噜噜狠狠_国产专区综合网_91欧美极品_国产二区在线播放_色欧美日韩亚洲_日本伊人午夜精品

Search

Nuclear Power

Thursday
06 Feb 2025

Streamlining Decommissioning

06 Feb 2025  by neimagazine   

 


Unit 3 of the Crystal River nuclear power plant is on an accelerated decommissioning programme

 Unit 3 at the Crystal River nuclear power plant in Florida, USA, saw the first use of an optimised segmentation process that was deployed as a method for accelerated decommissioning. This innovative approach for dismantling nuclear reactors was developed by Orano Decommissioning Services and is designed to reduce the volume of waste for disposal, as well as the amount of segmentation work required on reactor structures. The goal is to reduce both the time required and the cost of decommissioning.

Located in Citrus County, Florida, USA, Unit 3 of the Crystal River nuclear power plant was a Babcock and Wilcox 860 MWe Pressurised Water Reactor (PWR). Commissioned in 1976 the plant operated for 33 years until it was permanently shut down by owner Duke Energy in 2013. In October 2020, Accelerated Decommissioning Partners (a joint venture between Orano Decommissioning Services and demolition company NorthStar Group Services) completed a transaction with Duke Energy to begin decontamination and dismantling of the plant nearly 50 years sooner than had been originally planned. Accelerated Decommissioning Partners (ADP) thus became the Nuclear Regulatory Commission (NRC) licensed operator responsible for decommissioning the plant and also acquired the used nuclear fuel and the Independent Spent Fuel Storage Installation (ISFSI) assets.

Cutting decommissioning and disposal costs

The main drivers in the cost and schedule of a reactor decontamination and decommissioning operation are typically the extent of segmentation work to be performed on the reactor components. This is necessary to reduce their size so they can be removed and packaged for storage, shipment, and disposal. Another key cost driver is the number, size, and classification of the waste packages generated by the dismantling process.

The most contaminated and activated components of a nuclear energy reactor are concentrated inside the reactor pressure vessel (RPV) and the reactor vessel internal (RVI) structures. Dismantling the RPV and RVI structures generates the waste with the highest classifications when compared to the rest of the radioactive waste generated during reactor dismantling, with components classified as Class B, C, and Greater-than-Class C (GTCC), generating the highest cost for packaging, transportation, and ultimately their disposal.

Optimising cost therefore involves being able to segregate and distribute the generated waste within the various classifications to minimise the volumes of the costliest and most radioactive portion of the waste, GTCC and Classes B and C. This consideration is balanced against the operational costs needed to achieve the desired segmentation plan and involves finding the ideal compromise working within the following constraints:

Capabilities and limitations of the segmentation technologies available to efficiently and safely perform the separation and size reduction of highly radioactive reactor components.

Operational costs, since the segmentation work is labour-intensive and time-consuming due to the complex environment in which the segmentation equipment is used and the highly radioactive nature of the components to be segmented.

Capacities in weight and volume of the existing packaging systems licensed to receive and store and/or transport the generated waste in each category, driving the maximum size of the segments generated in each category. The high cost of procuring, transporting, and disposal or storage of the waste containers encourages achieving the highest packaging efficiency, which drives decisions towards more extensive segmentation of the reactor components.

The optimal segmentation strategy is driven by the goal to minimise the extent of the workplan engineering, on-site segmentation work, and the number of waste packages and shipments that typically come with the standard Full Segmentation strategy. One radical alternative to full segmentation is the “one piece” reactor removal approach, where the entire reactor vessel is shipped, including some of the reactor vessel internals. This solution has been successfully implemented in previous projects but involves very large packages and conveyance systems, which will be constrained by the limitations of the available transportation route infrastructure.

A compromise between the ‘full segmentation’ and ‘one piece’ strategies resolves these challenges by accommodating the transportation logistics restrictions with custom-designed waste containers large enough to substantially reduce the reactor component size reduction effort, while remaining transportable within existing road and transportation infrastructure capabilities.

Segmentation at Crystal River 3

By modelling the operating history of the reactor and how the various components had been irradiated and activated it was possible to predict the expected waste classification of each part of the Crystal River 3 reactor vessel and and its structures. The GTCC components are found in the core region of the internals and consist of the core barrel and baffle assembly, the surveillance capsule holders, surveillance capsule dosimeters, and in-core instrumentation detectors. These components have to be separated and segregated from the rest of the components so they can be packaged in containers that are stored onsite within the existing ISFSI until a final repository is available. Class B and C components are located in the other areas closest to the core region and consist of the control rod guide tube assemblies, upper core grid, the thermal shield, and lower internals assembly. Class A components include the plenum cover, plenum cylinder, core support shield assembly, reactor vessel, and vessel head.

As a first step in the process the reactor internals were segmented, extracted, and separated into two categories:

GTCC waste to be handled, packaged, and stored using conventional methods, such as Orano’s NUHOMS® interim dry storage systems

Contaminated and activated LLW internal structures

The internals were removed from the RPV, and precisely segmented underwater using remotely operated mechanical tools to segregate the GTCC components.

The emptied reactor vessel was then repacked using a tightly engineered placement based on each piece’s characterisation, with the highest activity components concentrated in the middle of the vessel. Less active low-level category waste was placed in the bottom and top sections. The reactor vessel and the repackaged internals were then immobilised in a specifically designed and qualified low-density cellular concrete mix to form the monolith, fixing the internals and providing radiation shielding.

The solid, grout-filled reactor vessel packed with waste was subsequently segmented into large sections with diamond wire saws and consistent with the internal waste materials distribution.

Outcomes of the optimised segmentation programme

The optimised segmentation and packaging strategy reduces the number of containers needed to receive the reactor vessel and vessel internals segments to a total of six. In contrast, a traditional reactor vessel dismantlement can generate up to 80 transport packages.

With optimised distribution of the activity within the monolith, the highest activity can be concentrated in one section and packaged into one Class B/C transportation and disposal package. The rest of the sections can be packaged into Class A packages. Two Rad Waste Canisters receive and store the GTCC portion of the reactor waste in the ISFSI. One Type B custom package is designed and licensed by the NRC to receive the middle section. One IP-2 metal container receives the top section, and two custom-designed and manufactured IP-2 supersacks receive the reactor head and bottom section.

Reactor dismantling operations at Crystal River 3 started in 2021. Components of the reactor cooling system including steam generators, main coolant pumps and motors, the pressuriser, and large bore piping were removed from the containment building and had been shipped off site for disposal by the end of October 2021. Segmentation of the reactor internals was conducted in 2022. Segregation, packaging, and on-site dry storage of the GTCC waste was completed in March 2023 while consolidation of the remaining internal structures into the vessel and grouting in preparation for final segmentation was concluded by the end of June 2023. Segmentation of the monolith was completed in October 2023.

Each section was packaged and shipped individually in a tailor-made container designed to transport and dispose of the waste in compliance with relevant regulations such as those of the NRC for Type B shipments and DOT for Industrial Packages, as well as the disposal site’s Waste Acceptance Criteria. All reactor segments were packaged and stored on site prior to off-site shipment to the Waste Control Specialists (WCS) disposal site in Andrews, Texas, in early 2024. A route survey determined that a combination of barge and road transportation offered the opportunity to ship packages as large as 16 feet (4.9m) high, 20 feet (6m) wide, and with a load of up to 450,000 kg, without road infrastructure modifications. This envelope formed the basis of the Optimized Segmentation strategy that was ultimately implemented.

Of the three segmented reactor vessel sections, only the middle section required an NRC-approved Type B package and an NRC Special Package shipping authorisation for this section was issued in August 2023. The two remaining reactor vessel segments – the bottom and top sections – only required shipping containers to comply with the DOT Industrial Package regulations (49 CFR 173).

Operations within the reactor building at Crystal River unit 3 were completed with the cleanup of the reactor cavity and the demobilisation of all equipment and staff from the reactor building by the end of October 2023, three years after the start of the project.

The optimised packaging plan and large container strategy significantly reduced the amount of segmentation work performed on the reactor structures and accelerated progress towards their removal from the containment building.

More News

Loading……
国产精品永久| 国模精品一区| 成人免费一区| 日韩黄色在线| 国产成人精品福利| 国产精品亚洲片在线播放| 国产精品jk白丝蜜臀av小说| 亚洲精品亚洲人成在线观看| av中文字幕一区二区| 欧美精品黄色| 日本中文字幕一区二区有限公司| 精品一区在线看| 99精品久久只有精品| 中文字幕第一区综合| 亚洲国产人成综合网站| 欧美三级三级三级爽爽爽| 精品国产乱码久久久久久老虎| 日本特黄a级高清免费大片| 婷婷婷国产在线视频| 97caopor国产在线视频| 色婷婷综合久久久中字幕精品久久 | 日韩你懂的在线播放| igao视频网在线视频| a天堂中文在线官网在线| abab456成人免费网址| 任你弄精品视频免费观看| 日韩高清欧美| 蜜桃传媒麻豆第一区在线观看| 91丨porny丨首页| 亚洲第一搞黄网站| 精品sm在线观看| 国产粉嫩一区二区三区在线观看| 国产丝袜视频在线播放| 亚洲精品福利| 99热这里只有成人精品国产| 成人丝袜视频网| 精品久久久久久国产91| 成人亚洲一区二区三区| av黄色在线| 久久久亚洲欧洲日产| 99成人在线| 91蝌蚪国产九色| 亚洲福利一二三区| 欧美艹逼视频| 成人短视频app| 欧美另类69xxxxx| 国内精品第一页| 亚洲午夜精品久久久久久久久| 欧美精品在线一区二区| av在线免费观看网站| 精品一区91| 免费亚洲一区| 一区二区三区中文字幕精品精品 | 啪啪激情综合网| 日韩电影免费在线| 亚洲专区一二三| 99久热re在线精彩视频| 亚洲精品mv| 狠狠色狠狠色综合日日tαg| 91在线视频网址| 日韩欧美一卡二卡| 亚洲综合图区| 教室别恋欧美无删减版| 国产+成+人+亚洲欧洲自线| 日本二三区不卡| 婷婷在线视频观看| 一区三区在线欧| 成人av在线影院| 日韩亚洲欧美中文三级| gogo久久| 日韩视频久久| 亚洲午夜免费电影| 久久电影中文字幕| 亚洲精华一区二区三区| 高清国产午夜精品久久久久久| 欧美性受xxxx黑人xyx性爽| 黄网页免费在线观看| 四季av一区二区凹凸精品| 国产日韩精品视频一区| 免费在线黄网| 狠狠一区二区三区| 暴力调教一区二区三区| 亚州av影院| 韩国精品视频在线观看| 日本怡春院一区二区| 色欧美88888久久久久久影院| 久久99精品久久久久久野外| 99热国内精品永久免费观看| 国产精品沙发午睡系列990531| av漫画网站| 欧美大片91| 成人av电影在线| 男人在线视频资源| 97精品久久| 国产校园另类小说区| 在线观看国产麻豆| 成人网18免费网站| 一区二区三区四区激情| 一级毛片视频在线观看| 欧美激情日韩| 欧美中文字幕一区二区三区亚洲 | 久久se这里有精品| 影音av资源站| 高潮按摩久久久久久av免费| 国产视频一区在线播放| 奇米影视888狠狠狠777不卡| 日韩伦理一区| 日韩人在线观看| 精品网站在线| 91麻豆国产福利在线观看| 日本韩国一区| 尤物在线精品| 欧美一级欧美三级在线观看| 激情视频亚洲| 亚洲图片欧美激情| 色呦呦呦在线观看| 国产综合色产在线精品| 国产超碰精品在线观看| 99久久婷婷国产综合精品电影√| 狠狠久久五月精品中文字幕| 最近高清中文在线字幕在线观看1| 国产一区二区精品久久91| 在线激情视频| 好吊一区二区三区| 日韩欧美国产一区在线观看| 91成人精品在线| 亚洲欧美中日韩| 丝袜诱惑一区二区| 91亚洲精品乱码久久久久久蜜桃| 国产有码在线| 久久99精品久久久| 日韩私人影院| 日韩电影在线观看网站| 男人天堂午夜在线| 夜夜爽av福利精品导航| xxxxx国产| 99国产精品| 中文字幕在线视频观看| 亚洲欧美久久久| 中文字幕在线二区| 日本欧美久久久久免费播放网| 91在线最新| 99精品久久| 最近中文字幕在线| 蜜臂av日日欢夜夜爽一区| 色中色在线视频| 国产精品一区2区| 伦xxxx在线| 99re热这里只有精品免费视频| 影音先锋在线视频| 91美女片黄在线观看| 97在线超碰| 日韩一区在线看| 精品国产一区二区三区性色av| 亚洲一区二区美女| www.亚洲一二| 91麻豆精品国产91久久久久| 久久视频国产| 天堂男人av| 久久99精品久久久久久| 日本孕妇大胆孕交无码| 久久久精品国产免费观看同学| 高清电影一区| 欧美日韩在线看| 欧美色图一区| 国产区视频在线观看| 天堂在线亚洲视频| yiren22亚洲综合伊人22| 91免费版在线| 成人影院网站ww555久久精品| 一本大道久久精品懂色aⅴ| 日韩久久精品网| 在线激情av| 91免费在线视频观看| 99久热在线精品视频观看| 欧美丰满高潮xxxx喷水动漫| 妖精视频成人观看www| h网站视频在线观看| 国产精品久久久久久久久免费桃花| 这里视频有精品| 精品国产一二三| 国产一区啦啦啦在线观看| 九色porny自拍视频在线观看| 亚洲一区二区三区四区不卡| 凹凸成人精品亚洲精品密奴| 日本免费视频| 久久青草欧美一区二区三区| 日韩精品久久久久久久软件91| 欧美一卡二卡三卡| 另类小说视频一区二区| japanese23hdxxxx日韩| 欧美日韩国产一级片| 日日摸夜夜添夜夜添精品视频| 欧美v亚洲v| 欧美视频在线一区| 日韩精品欧美成人高清一区二区| 性欧美videoshd高清| 日韩欧美在线视频免费观看| 亚洲久久一区| 日韩成人av电影|