Jacobs Outlines Approach to Indonesian Geothermal Plant

15 Oct 2020  by Sarah Smith   

Jacobs has outlined its role in providing owners engineering services for Stage 1 of PT Supreme Energy Muara Laboh’s geothermal power plant, as well as its continued support on the Stage 2 development plant.

Already the world’s second largest geothermal producer and with an abundance of natural resources, Indonesia is well placed for the transition to renewable energy. However, its energy sector still relies primarily on coal, oil and gas to power its electricity grid. As it stands, only 7% of energy is generated from renewable sources.

In 2017, the Indonesian government set a target of 23% renewable energy by 2025. Geothermal power will play a key role in helping the government reach its target and current generation capacity set to quadruple, growing from 1800 MW to 7200 MW. One of the projects helping the government reach this target is the Muara Laboh Geothermal Power Plant in South Solok, West Sumatra.

Jacobs’ work on the project began in 2014. The company’s team was engaged by PT Supreme Energy Muara Laboh (SEML)—a joint venture between PT Supreme Energy, ENGIE and Sumitomo Corporation—to provide Owner’s Engineering (OE) services for Stage 1 of the project. Services included developing process and layout concepts, plant capacity modelling, project cost estimate, concept process engineering, technical specifications, technical bid documentation, bid evaluation, design review, construction and commissioning support for an 85 MWe geothermal plant.

Stage 1 was completed in December 2019. It is the first project in the West Sumatra region to generate electricity from geothermal steam resources using a dual flash turbine and geothermal steam gathering system.

Tackling challenging site conditions

Project delivery challenges matched the complexity and magnitude of the project itself. The plant is located around 150 km south-east of Padang, spread over approximately 154 acres (62.3 hectares) of land and borders the Kerinci National Park. While the site had many positive attributes, including its proximity to production wells and feasibility of gravity injection and separation from geothermal brine, it also presented significant challenges. These included high seismic risk, steep terrain, limited space, potential for land slips, variable ground conditions and potential exposure to heavy rain.

Jacobs specified extensive risk management and robust design requirements during the early stages of the project. This meant bringing together a team with a deep understanding of the processes, risks and uncertainties presented and the credibility and foresight to serve as a trusted advisor and support key stakeholders to deliver a successful outcome.

Designing with the future in mind

Jacobs’ understanding of SEML’s future plans for the Stage 2 development (an additional 65 MW capacity) shaped the company’s design approach and it avoided design decisions and compromises that might impact the subsequent development. Extra attention and careful planning went into the detailed design for the steamfield to protect key physical and process interfaces, and minimise the potential impact on operations during Stage 2 development.

The team also had a significant input into developing robust solutions for pads, drainage, engineered fill and cut slopes to provide a resilient overall solution that would protect it for a minimum 50-year design life in what is a geologically unstable area prone to high levels of seismic activity and high intensity rainfall.

Leveraging world-class global expertise

The project presented many challenges. For example, when construction started the geothermal resource capacity was still uncertain. So, when drilling and testing during construction found the site had less capacity than originally thought, the design had to be quickly adapted to match the new resource capability. Challenging and highly variable soil conditions were a constant battle on-site during construction.

Jacobs’ geothermal knowledge and experience collected from other geothermal projects across the world was key to managing risks and providing the right solutions. Specialist technical staff completed in excess of 430 days on-site in order to support the client and assume key responsibilities in supervising the construction and commissioning works. Engineering teams in Indonesia and New Zealand were supported by specialists based in seven countries around the globe. This combination was key to positively influencing the design and resolving site and construction issues as they arose, while ensuring a resilient and flexible design for future development.

Delivering social benefits to the community

The project has delivered significant benefits to the local community, including creating employment opportunities for an estimated 1,200 people over the 30-month construction period. Gone are the days when the people of South Solok experienced power outage up to three times a day. Now powering up to 340 000 households in the province, the geothermal plant delivers an estimated 1 730 000 MWh per year to the Sumatra grid through a 150 KV High Voltage Transmission Line (SUTT).

Jacobs continues to support SEML on the Stage 2 development plant which will provide additional long-term security of steam supply to the geothermal development. The new development will expand Muara Laboh Geothermal Plant’s capacity by an additional 65 MWe and is expected to begin construction in 2021.

This article is reproduced at www.energyglobal.com

More News

Loading……
天堂俺去俺来也www久久婷婷| 国产无一区二区| 欧美xxx在线观看| 国产精品成人一区二区不卡| 欧美激情第二页| 欧美全黄视频| 可以免费看不卡的av网站| 麻豆专区一区二区三区四区五区| 精油按摩中文字幕久久| 成人免费av在线| 日本一区二区三区在线观看| 亚洲精品亚洲人成人网在线播放| 婷婷激情综合网| 欧美日韩精品免费| 啊啊啊好爽视频| 欧美少妇另类| 96av在线| 2021年精品国产福利在线| 精品一区免费| 亚洲福利精品| 激情久久五月天| 国产亚洲综合色| 五月天丁香久久| 日韩一级精品视频在线观看| 色av一区二区三区| 在线免费观看黄色网址| 中文字幕在线高清| 亚洲国产aⅴ精品一区二区| 手机在线电影一区| 日本大胆欧美人术艺术动态| 久久影音资源网| 欧美色播在线播放| 日本xxxxxx| 韩国中文字幕在线| 国产一区二区三区国产精品| 天天色综合色| 国产乱妇无码大片在线观看| 国产精品嫩草影院com| 懂色av影视一区二区三区| 婷婷色播视频| 波多野结依一区| 色婷婷狠狠五月综合天色拍| 亚洲看片免费| 久久久噜噜噜久久中文字幕色伊伊| 精品久久久久久中文字幕一区奶水| 天天综合天天操| 日本动漫理论片在线观看网站| 91精品啪在线观看国产爱臀| 1000部精品久久久久久久久| 久久久久88色偷偷免费| 在线播放国产精品二区一二区四区| 欧美美女搞黄| 日本一区二区三区电影免费观看| 精品白丝av| 欧美国产一区二区| 欧美精品黑人性xxxx| 第三区美女视频在线| 欧美日本三级| 香蕉视频成人在线观看| 亚洲免费观看高清完整版在线观看 | 影视先锋av在线| 免费黄色网页在线观看| 色综合www| 国产91精品露脸国语对白| 日韩欧美在线视频观看| 9色在线视频网站| 精品素人av| 成人蜜臀av电影| 欧美丰满美乳xxx高潮www| www视频在线看| 欧美熟乱15p| 欧美国产丝袜视频| 中文字幕123| 亚洲一区二区三区四区电影| 蜜臀99久久精品久久久久久软件| 色综合天天狠狠| а天堂中文在线官网| 久久精品久久久| 亚洲人123区| 免费播放片a高清在线观看| 蜜桃久久久久| 久久你懂得1024| 国模私拍视频| 国产一级成人av| 91在线视频网址| 高清日韩av| 奇米影视777在线欧美电影观看| 高清av一区二区| 成年人视频免费看| 久久精品国产福利| 国产激情91久久精品导航| 精品捆绑美女sm三区 | 欧美一区二区国产| 在线看片国产福利你懂的| 国产精品日韩久久久| 一本一道久久a久久精品| 色综合999| 国产亚洲欧洲| 制服丝袜亚洲网站| 成人精品视频在线观看| 99精品视频一区二区| 美国成人av| 亚洲成人tv| 欧美日韩国产综合新一区 | 精品视频黄色| 日韩一区在线看| 91se在线| 激情久久中文字幕| 欧美日韩国产美| 国产精品一级在线观看| 2024国产精品| 日本免费视频在线观看| 久久xxxx精品视频| 5858s免费视频成人| 精品一区二区三区视频在线播放| 久久综合久久鬼色| 欧美私人网站| 日韩一区欧美二区| 大胆高清日本a视频| 久久久综合色| 欧美日韩国产精品成人| 国产66精品| 一区二区激情小说| 日韩一区二区三区在线免费观看| 成年人国产精品| 在线播放日本| 韩国精品一区二区| 免费在线毛片| 日本不卡一二三区黄网| 激情视频免费观看在线| 国内精品久久久久国产盗摄免费观看完整版 | 6080午夜不卡| 国产永久精品大片wwwapp| 91久久一区二区| 91精品尤物| 精品日本美女福利在线观看| 日韩视频一二区| 一区二区三区在线高清| av日韩在线免费观看| 一区二区三区丝袜| 国产一区二区色噜噜| 亚洲精品一二三四区| 粉嫩av一区二区三区四区五区| 亚洲欧美日韩综合aⅴ视频| 日韩电影网站| 日韩毛片一二三区| 四虎影视精品永久在线观看| 亚洲精品videosex极品| av在线亚洲一区| 婷婷成人激情在线网| 激情小说一区| 在线电影一区二区三区| 久久一区二区三区电影| 国产剧情av在线| 性一交一乱一区二区洋洋av| 伊大人久久香线焦宗合一75大| 日韩vs国产vs欧美| 在线观看二区| 久久久国产精品麻豆| 欧美日韩在线精品一区二区三区激情综合| 国产精品成人一区二区三区夜夜夜| 日本精品网站| 精品久久中文字幕久久av| 亚洲精品小区久久久久久| 欧美一区二区三区在线视频| 国产精品久久| 亚洲kkk444kkk在线观看| 国产高清一区日本| 3d欧美精品动漫xxxx无尽| 亚洲成人在线网站| 精品理论电影| 屁屁影院在线观看| 懂色av一区二区在线播放| 激情都市亚洲| 欧美私模裸体表演在线观看| 一区二区三区国产精华| 女人偷人在线视频| 久久精品视频网| 国产成人精品福利| www.天天操| 国产精品91xxx| 欧美性猛交xxx高清大费中文| 欧美日韩美女在线观看| 91成人网在线观看| 最新国产在线观看| 伊人一区二区三区| 久久福利综合| 成人高清网站| 一区二区三区日韩精品视频| 国产一区日韩| 一级在线免费观看| 国产欧美日韩综合精品一区二区| 欧美美女在线直播| av三级在线播放| 91污片在线观看| 麻豆精品少妇| 欧美日韩国产中文字幕在线| 亚洲综合清纯丝袜自拍| 亚洲成人中文| 男人最爱成人网|